Versant Power’s oldest transformer is replaced

Release Date:  06-07-2023

Ells 1

Ellsworth, Maine
 – Over the past few months, Versant crews have been upgrading the Ellsworth Falls substation with new equipment. Work involved replacing the oldest transformer in Versant’s fleet, a 73-year-old transformer that was removed this spring and replaced with a modern one. The new transformer went into commission this week.

“The upgrade ensures more reliable service to over 9,000 customers through Ellsworth, Deer Isle, Brooklin, Blue Hill, Surry and Brooksville,” said Versant’s Chief Operating Officer Paul Miller, “Customers receiving power from this substation are now also connected to the Boggy Brook substation in Ellsworth, which can serve as a back-up power source in the event that service is interrupted.”

After the aged transformer was removed, the existing concrete below it was repurposed, and the surrounding area was prepped for a new device. Work included digging and installing two identical series of conduits for protection, an ‘A’ option and ‘B’ contingency option for increased reliability.

Later this year, further improvements are planned for the Ellsworth Falls substation. A circuit switch will be replaced with a more modern circuit breaker for advanced protection. Both projects allow for upgraded technology that will help the Versant team monitor equipment and controls and respond to outages sooner.

Improvements at the substation involved Versant engineers, line crews, power system technicians, environmental team members and system operators along with the help of Virginia Transformer Corp. representatives.

Work at the substation is expected to be completed by spring 2024. For more Versant Power news, please visit versantpower.com.


Ells Test 2

Ells Test 3
Photos: Versant Power System Technicians test the new transformer before it is commissioned.

Please Identify Your Service Area

Click on your district on the map, or select a zip code or town from the lists.

Select Your District on the Map Below

Maine Public Service District Bangor Hydro District
or

or

Versant Power provides electric delivery service to two areas – the Bangor Hydro District and the Maine Public District.

            The Bangor Hydro District includes Hancock, Piscataquis and Washington Counties and most of Penobscot County.
            The Maine Public District serves Aroostook County and a small piece of Penobscot County.

Because some information varies by District, please identify your District on the map above, or enter your town or zipcode. If you need information on both Districts,  switch back and forth at any time by selecting the district selector button.

If the browser you are using has cookies enabled, you will only have to make this selection once.( If your browser has cookies disabled your selection will be remembered until you close the browser, but not when you return to the site.)